Prior notice and health & safety plan: when are they mandatory?
A prior notice is required for every construction site lasting more than 30 working days with more than 20 workers at the same time, or exceeding 500 person-days. A health & safety plan (SiGe-Plan) is mandatory if several employers are involved and, in addition, a prior notice is required or particularly dangerous work is carried out.
When is a prior notice required?
Under § 2 (2) of the Construction Site Ordinance, if
- the work is expected to last more than 30 working days and more than 20 workers are employed at the same time, or
- the scope of the work is expected to exceed 500 person-days.
A person-day is the work of one person over one shift. The prior notice must reach the competent authority at least two weeks before the site is set up – in Bavaria, the trade supervisory office of the district government. It is displayed visibly on site and updated if there are significant changes.
When is a health & safety plan mandatory?
Under § 2 (3) BaustellV, the health and safety plan (SiGe-Plan) must be drawn up before the site is set up if employees of several employers work on it and
- a prior notice has to be submitted or
- particularly dangerous work under Annex II is carried out.
Particularly dangerous work includes, among other things, work with a risk of falling from more than 7 m, work with a risk of being buried in excavations or trenches deeper than 5 m, work less than 5 m from high-voltage lines, and the assembly and dismantling of solid building elements moved by power-driven lifting equipment.
What does the health & safety plan contain?
- the occupational safety regulations applicable to the site
- hazards arising from the construction process and from the interaction of trades
- measures for particularly dangerous work
- shared safety facilities such as scaffolding, fall protection and traffic routes
The health & safety plan is updated during construction if processes or companies change.
Overview: what do I need when?
| Situation | Coordinator | Prior notice | H&S plan | File for later work |
|---|---|---|---|---|
| One employer, small site | no | no | no | no |
| One employer, large site | no | yes | no | no |
| Several employers, small site | yes | no | only for dangerous work | yes |
| Several employers, large site | yes | yes | yes | yes |
“Large site” = more than 30 working days and more than 20 workers at the same time, or more than 500 person-days. “Several employers” also applies if the companies work one after the other.
Frequently asked questions
Who is responsible for the prior notice and health & safety plan?
The building owner. They can delegate these tasks to a third party, for example the SiGeKo (§ 4 BaustellV).
What happens if the prior notice is missing?
This is an administrative offence under § 7 BaustellV and can be punished with a fine.
Prior notice and health & safety plan from a single source
Flight Event prepares the prior notice, health & safety plan and file for later work, and coordinates your site in Erlangen, Nuremberg, Fürth and Franconia.
Sources: Construction Site Ordinance (gesetze-im-internet.de) · Author: Flo Popp, SiGeKo according to RAB 30 · As of: November 2026