Do I need a SiGeKo when building a house?

Yes – even when building a detached house, you usually need a SiGeKo (health and safety coordinator). The German Construction Site Ordinance applies to private building owners just as it does to commercial ones – as soon as employees of several companies work on your site, even one after the other.

When a SiGeKo is mandatory for house building

Under § 3 (1) of the Construction Site Ordinance, the building owner must appoint one or more suitable coordinators if employees of several employers work on the site. In a typical house build these are the shell builder, carpenter, roofer, electrician, plumber and other trades – so the obligation almost always applies.

It makes no difference whether the companies work at the same time or one after the other. Small conversions with several trade firms are also covered.

Exceptions and special cases

  • Only one company: If a single general contractor builds with its own employees, no coordinator is needed. If the general contractor uses subcontractors, there are again several employers.
  • Your own work: Work you carry out yourself without employees does not count as an employer – but the companies you commission do.
  • Coordinating yourself: You may take on the task yourself if you are suitably qualified. This requires construction expertise, occupational safety knowledge and coordinator knowledge as described in the RAB 30 rule.
  • Delegation: You can delegate your duties to a third party under § 4 BaustellV, for example to your architect or a SiGeKo. This should be done in writing.

What the SiGeKo does when building a house

  • Coordinating the trades so that they do not endanger each other, e.g. with scaffolding, roof openings or excavations
  • Regular site inspections with minutes
  • Prior notice and health & safety plan where required
  • File for later work on the house, for example for maintenance of roof and façade

Why it pays off for building owners

The building owner remains responsible for appointing the coordinator. If an accident happens on site and no coordinator was appointed, this can have legal consequences for the owner. A SiGeKo involved early also helps to plan processes and interfaces properly.

Frequently asked questions

Can my architect act as SiGeKo?
Yes, if they hold the qualification according to RAB 30 and the service is explicitly commissioned. It is not automatically included in the architect's contract.

When should I appoint the SiGeKo?
Before construction starts, ideally during the planning phase. Coordination already begins while the execution is being planned.

What does it cost?
That depends on the construction period, trades and inspections. More in the guide What does a SiGeKo cost?

A SiGeKo for your house build in Franconia

Flight Event coordinates private and commercial building projects in Erlangen, Nuremberg, Fürth, Bamberg and the surrounding area.

Our SiGeKo services Send an enquiry

Sources: Construction Site Ordinance (gesetze-im-internet.de) · Author: Flo Popp, SiGeKo according to RAB 30 · As of: November 2026